川消氣體滅火系統模擬啟動試驗的注意事項
來源:http://m.xintli.net/ 日期:2022-07-19
為驗證氣體滅火系統的可靠性能,氣體滅火系統工程建設完成后,需要進行模擬啟動試驗。模擬啟動試驗應在氣體滅火系統、報警系統等安裝調試完成后進行。那么在進體滅火系統模擬啟動試驗時應該注意什么?
In order to verify the reliable performance of the gas fire extinguishing system, a simulated start-up test is required after the completion of the gas fire extinguishing system project. The simulated start-up test shall be carried out after the installation and commissioning of gas fire extinguishing system, alarm system, etc. So what should we pay attention to when conducting the simulated start-up test of gas fire extinguishing system?
測試依據:
Test basis:
《氣體滅火系統施工及驗收規范》GB50263-2007
Code for construction and acceptance of gas fire extinguishing systems (gb50263-2007)
測試內容:
Test content:
1.手動開始實驗
1. Start the experiment manually
2.自動啟動測試
2. Automatic start test
準備:
get ready:
1、氣體報警系統和氣體滅火系統已安裝調試完畢,具備測試工具(秒表、聲級計、萬用表、點位儀、點位測試儀等)。
1. The gas alarm system and gas fire extinguishing system have been installed and debugged, and have test tools (stopwatch, sound level meter, multimeter, point position meter, point position tester, etc.).
2.人員應檢查所有線路是否連接良好。
2. Professionals should check whether all lines are well connected.
3、在人員的指導下,拆下啟動氣體滅火系統的電磁閥,進行模擬試驗。
3. Under the guidance of professionals, dismantle the solenoid valve that starts the gas fire extinguishing system and conduct a simulation test.
測試方法:
Test method:
1、手動模擬開機測試可進行如下:
1. The manual simulated startup test can be carried out as follows:
(1)按下手動啟動按鈕,觀察相關動作信號及聯動設備是否正常運行(如聲光報警、啟動輸出端負載響應、關閉通風空調等)。
(1) Press the manual start button and observe whether the relevant action signals and linkage equipment operate normally (such as audible and visual alarm, starting the load response at the output end, turning off the ventilation and air conditioning, etc.).
(2)手動啟動壓力信號反饋裝置,觀察相關保護區門外的氣體排放指示燈是否正常。
(2) Manually start the pressure signal feedback device and observe whether the gas emission indicator outside the relevant protection zone is normal.
2、自動模擬開機測試可按以下方法進行:
2. The automatic simulated startup test can be carried out according to the following methods:
(1)將滅火控制器的啟動輸出端連接到滅火系統相應保護區的驅動裝置上。驅動裝置應與閥作用機構脫開。也可以用與驅動器的啟動電壓和電流相同的負載來代替。
(1) Connect the starting output end of the fire extinguishing controller to the driving device of the corresponding protection area of the fire extinguishing system. The driving device shall be disconnected from the valve action mechanism. It can also be replaced by a load with the same starting voltage and current as the driver.
(2)人工模擬火警在保護區內做出任何動作,觀察單次火警信號輸出(如警鈴、蜂鳴器等)后相關報警設備是否正常動作。
(2) Manually simulate the fire alarm to make any action in the protection area, and observe whether the relevant alarm equipment operates normally after a single fire alarm signal output (such as alarm bell, buzzer, etc.).
(3)手動模擬一個火災報警器保護區內的另一個火災探測器,觀察復合火災報警信號(如聲光報警、啟動負載)輸出后相關動作信號及聯動設備是否正常運行在輸出端,關閉通風和空調)。、防火閥等)。
(3) Manually simulate a fire alarm to activate another fire detector in the protection area, and observe whether the relevant action signals and linkage equipment operate normally at the output end after the output of the composite fire alarm signal (such as audible and visual alarm, starting load), and turn off ventilation and air conditioning) Fire damper, etc.).

測試結果的判斷:
Judgment of test results:
Chuanxiao Xiaobian believes that the simulation start-up test results should meet the following requirements:
1、延遲時間與設定時間一致,響應時間符合要求;
1. The delay time is consistent with the set time, and the response time meets the requirements;
2、聲光報警信號正確;
2. Sound and light alarm signals are correct;
3、聯動設備動作正確;
3. The action of linkage equipment is correct;
4、驅動裝置可靠。
4. The driving device is reliable.
6、測試注意事項:
6. Test precautions:
1、本試驗需要嚴格按照人員的指導進行,以免損壞設備或傷害人員。
1. This test needs to be carried out in strict accordance with the guidance of professionals to avoid damage to equipment or injury to personnel.
2、試驗前應將電磁閥從瓶組上拆下,以免誤操作啟動氣體滅火系統。
2. Before the test, the solenoid valve should be removed from the bottle group to avoid misoperation and start the gas fire extinguishing system.
3、試驗結束后,應將氣體滅火系統復位檢查。
3. After the test, reset the gas fire extinguishing system for inspection.
氣體滅火系統的模擬試驗是每個項目完成后都需要進行的試驗。主要目的是保證氣體滅火系統的可靠性。需要人員進行測試。用戶還可以了解更多,以確保安裝的氣體滅火系統。設備可以正常使用。更多相關內容就來關注網站
http://m.xintli.net信息吧!
The simulation test of gas fire extinguishing system is required after the completion of each project. The main purpose is to ensure the reliability of the gas fire extinguishing system. Professional personnel are required for testing. Users can also learn more to ensure the installation of gas fire extinguishing system. The equipment can be used normally. Follow the website for more relevant content http://m.xintli.net Information!