川消大空間滅火裝置的一種,由大空間滅火裝置、信號閥組、水流指示器等組件及管道、供水設施等組成,能在發生火災時自動探測著火部位,并主動噴水。這種系統需要在建筑內部裝修和系統施工完成后進行系統調試,下面是大空間智能型主動噴水滅火系統的調試過程。
The large space intelligent active sprinkler system is one of the large space fire extinguishing devices of Chuanxiao. It is composed of large space fire extinguishing devices, signal valve groups, water flow indicators and other components as well as pipelines and water supply facilities. It can automatically detect the fire position in case of fire and actively spray water. This system needs to be commissioned after the interior decoration and system construction of the building are completed. The following is the commissioning process of the large space intelligent active sprinkler system.
1、水源測試應符合下列要求:
1. The water source test shall meet the following requirements:
1)當釆用地下消防水池作水源時,按設計要求核實消防水池的容積、水質以及消防儲水不作它用的技術措施;
1) When the underground fire pool is used as the water source, the volume and water quality of the fire pool and the technical measures that the fire water is not used for other purposes shall be verified according to the design requirements;
2)當采用市政自來水直接供水時,按設計要求核實市政自來水的水壓、水質、進水管數量,各進水管的供水量、是否設置了檢修閥門和倒流防止器;
2) When municipal tap water is used for direct water supply, the water pressure, water quality, quantity of water inlet pipes, water supply quantity of each water inlet pipe and whether maintenance valves and backflow preventers are set shall be verified according to the design requirements;
3)當釆用屋頂水箱、高位水池直接供水時,按設計要求核實屋頂水箱、高位水池的儲水容積、水質、設置高度、補水時間以及消防儲水不作它用的技術措施;
3) When the roof water tank and high-level water tank are used for direct water supply, the water storage volume, water quality, setting height, water replenishment time and technical measures that the fire water storage is not used for other purposes shall be verified according to the design requirements;
4)按設計要求核實消防水泵接合器的數量和供水能力,并通過移動式消防水泵做供水試驗進行驗證。
4) The quantity and water supply capacity of fire pump adapters shall be verified according to the design requirements, and verified by water supply test of mobile fire pump.
2、消防水泵調試應符合下列要求:
2. Commissioning of fire pump shall meet the following requirements:
1)消防水泵的供電電源應釆用消防電源;
1) The power supply of fire pump shall be fire power supply;
2)以手動方式啟動消防水泵時,消防水泵應在手動按鈕按下后20s內投入正常運行;當大空間滅火裝置自動啟動時,消防水泵應在大空間滅火裝置發出報警信號后20s內投入正常運行;
2) When the fire pump is started manually, the fire pump shall be put into normal operation within 20s after the manual button is pressed; When the large space fire extinguishing device starts automatically, the fire pump shall be put into normal operation within 20s after the large space fire extinguishing device sends out the alarm signal;
3)以備用電源切換方式或備用泵切換起動消防水泵時,消防水泵應在20s內投入正常運行。
3) When the fire pump is started in the standby power supply switching mode or the standby pump switching mode, the fire pump shall be put into normal operation within 20s.
3、穩壓泵調試
3. Stabilized pressure pump commissioning
穩壓泵應按設計要求進行調試,當達到設計啟動條件時,穩壓泵應立即啟動;當達到系統設計壓力時,穩壓泵應自動停止運行;當消防主泵啟動時,穩壓泵應停止運行。
The stabilized pressure pump shall be commissioned according to the design requirements. When the design starting conditions are met, the stabilized pressure pump shall be started immediately; When the system design pressure is reached, the stabilized pressure pump shall automatically stop operation; When the main fire pump is started, the stabilized pressure pump shall stop running.

4、水流指示器和信號閥調試應符合下列要求:
4. Commissioning of water flow indicator and signal valve shall meet the following requirements:
1)大空間滅火裝置射水滅火時,水流指示器應輸出報警信號;
1) The water flow indicator shall output an alarm signal when the fire extinguishing device in large space fires;
2)信號閥應準確發出閥門打開或關閉的電信號。
2) The signal valve shall accurately send the electric signal of opening or closing the valve.
5、排水裝置調試
5. Drainage device commissioning
試驗過程中,系統排出的水應通過排水設施全部排走,或排回消防水池。
During the test, the water discharged from the system shall be completely discharged through the drainage facilities or returned to the fire pool.
6、電源裝置調試應符合下列要求:
6. The commissioning of power supply device shall meet the following requirements:
1)電源裝置的容量應符合設計和現行有關標準的要求;
1) The capacity of power supply device shall meet the requirements of design and current relevant national standards;
2)電源裝置的交流輸入和直流備用輸入(蓄電池組)應能自動切換;
2) The AC input and DC standby input (battery pack) of the power supply device shall be able to switch automatically;
3)電源裝置的交流輸入和直流備用輸入切換時,不應影響大空間智能滅火裝置的工作狀態;
3) When the AC input and DC standby input of the power supply device are switched, the working state of the large space intelligent fire extinguishing device shall not be affected;
4)電源裝置的直流備用輸入(蓄電池組)充放電功能正常。等等。
4) The charging and discharging functions of the DC standby input (battery pack) of the power supply unit are normal. wait.
其實,系統調試是為了檢驗其達到驗收規范標準所進行的全系統檢測、調整和實驗,這一過程對于整個消防工程來講都十分重要,所以調試過程一定要嚴謹進行!更多相關事項的了解就來我們網站
http://m.xintli.net進行咨詢吧。
In fact, the system commissioning is the whole system inspection, adjustment and experiment to verify that it meets the acceptance specifications and standards. This process is very important for the whole fire engineering, so the commissioning process must be carried out strictly! For more information, please visit our website http://m.xintli.net Let's consult.